Wednesday, April 18, 2012

PMP Question #1

By
PMP Question #1
You are appointed as the project manager of a $460 million construction project. All the following are characteristics of a project except:

A. Temporary endeavor
B. Creates a unique product, service or result
C. Short in duration
D. Definite beginning and end

What is your answer? Why? Please leave your comments. I will upload the correct answer tomorrow.

5 comments:

  1. C - Short in duration

    Reply
  2. Interesting article. For my PMP exam prep, I found useful material on PMStudy, They provide a complimentary 200 question simulated test and we can take also other practice tests starting at $25.The PMP Certification

    Reply