The world of stocks and investments can be tricky; understanding the ins and outs of equities is essential to successful trading. Regarding stocks, there are two main types: common shares and preferred shares. While both present excellent opportunities for returns, they differ significantly in their structure—and that's why unpacking these differences is so important.
Saturday, November 19, 2016
Answers to Mock PMP Exam Questions
By
With
4 comments:
I have written a short list of 10 mock PMP exam questions. In this article, I have given the correct answer choices to those PMP exam questions. Relevant explanations are also given for you to understand why the answer choice is the best choice available.
If you still have any doubts, you can drop your comments in the section below. If you feel the correct answer choice should be something else, please provide your line of thought and we can discuss.
Explanation: The Project Manager is in the Plan Schedule Management process; this is the process of establishing the policies, procedures and documentation for planning, developing, managing, executing and controlling the project schedule. Expert judgment, Meetings and Analytical Techniques are all the Tools & Techniques of Plan Schedule Management.
The only exception is Decomposition. Decomposition is used as a tool in "Create WBS" and "Define Activities".
Explanation: Historical information, Templates and Change Control Procedures are all examples of Organizational Process Assets. Organizational Structure is not an Organizational Process Asset; it is part of the Enterprise Environmental Factors.
Explanation: Define Activities is the process of identifying and documenting the specific actions to be performed to produce the project deliverables.The output of define activities is a list of activities.
So, the immediate next action would be to identify the relationships among the activities. This process of identifying and documenting the relationships among project activities is called "Sequence Activities".
So, the correct answer is "Sequence Activities".
Explanation: The relationship is: Finish laying of road =>Wait 28 days => Start using the road.
Here, 28 days is the lag for which the next activity should wait. So, the relationship is Laying of road => FS+28d => Start of use of the road.
The correct answer choice is Option C.
Explanation: Resource leveling is a technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
Explanation: A project is a temporary endeavor; but, it does not necessarily mean the duraion of the project is short. Please note that repetitive elements may be present in some project deliverables and activities; but, this repetition does not change the fundamental, unique characteristics of the project work. You also should understand a project can involve a single or mulitple individuals, a single organization or multiple organizations.
Explanation: The project charter is created long before you start identifying work packages and activities. Project charter typically contains only high level information while work packages are created with detailed information.
Explanation: Delphi technique is an information gathering technique. The remaining three are quantitative risk analysis techniques
Explanation: FV = PV(1+i)^n. In this problem, Future Value FV = $48,400, rate of return I = 10% and number of years n =2. Substituting these values in the formula, you will get Present Value PV = $40,000
Explanation: Project B was preferred over project A. So, the opportunity cost would be the NPV of project A, which was not chosen.
If you still have any doubts, you can drop your comments in the section below. If you feel the correct answer choice should be something else, please provide your line of thought and we can discuss.
Answers to Mock PMP Exam Questions
Mock PMP Exam Question No: 1
Correct Answer: CExplanation: The Project Manager is in the Plan Schedule Management process; this is the process of establishing the policies, procedures and documentation for planning, developing, managing, executing and controlling the project schedule. Expert judgment, Meetings and Analytical Techniques are all the Tools & Techniques of Plan Schedule Management.
The only exception is Decomposition. Decomposition is used as a tool in "Create WBS" and "Define Activities".
Mock PMP Exam Question No: 2
Correct Answer: BExplanation: Historical information, Templates and Change Control Procedures are all examples of Organizational Process Assets. Organizational Structure is not an Organizational Process Asset; it is part of the Enterprise Environmental Factors.
Mock PMP Exam Question No: 3
Correct Answer: CExplanation: Define Activities is the process of identifying and documenting the specific actions to be performed to produce the project deliverables.The output of define activities is a list of activities.
So, the immediate next action would be to identify the relationships among the activities. This process of identifying and documenting the relationships among project activities is called "Sequence Activities".
So, the correct answer is "Sequence Activities".
Mock PMP Exam Question No: 4
Correct Answer: CExplanation: The relationship is: Finish laying of road =>Wait 28 days => Start using the road.
Here, 28 days is the lag for which the next activity should wait. So, the relationship is Laying of road => FS+28d => Start of use of the road.
The correct answer choice is Option C.
Mock PMP Exam Question No: 5
Correct Answer: BExplanation: Resource leveling is a technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
Mock PMP Exam Question No: 6
Correct Answer: BExplanation: A project is a temporary endeavor; but, it does not necessarily mean the duraion of the project is short. Please note that repetitive elements may be present in some project deliverables and activities; but, this repetition does not change the fundamental, unique characteristics of the project work. You also should understand a project can involve a single or mulitple individuals, a single organization or multiple organizations.
Mock PMP Exam Question No: 7
Correct Answer: CExplanation: The project charter is created long before you start identifying work packages and activities. Project charter typically contains only high level information while work packages are created with detailed information.
Mock PMP Exam Question No: 8
Correct Answer: DExplanation: Delphi technique is an information gathering technique. The remaining three are quantitative risk analysis techniques
Mock PMP Exam Question No: 9
Correct Answer: BExplanation: FV = PV(1+i)^n. In this problem, Future Value FV = $48,400, rate of return I = 10% and number of years n =2. Substituting these values in the formula, you will get Present Value PV = $40,000
Mock PMP Exam Question No: 10
Correct Answer: CExplanation: Project B was preferred over project A. So, the opportunity cost would be the NPV of project A, which was not chosen.
Thursday, January 14, 2016
PMP Exam Questions and Answers - FREE
By
With
20 comments:
Here, you will find a list of mock PMP exam questions that are designed to represent the actual PMP exam questions as closely as possible. These free mock PMP exam questions are framed based on my personal experience in appearing for the PMP exam and the PMI-RMP exam.
The real PMP exam questions are not easier; but the more you practice, it would be better for you to face the actual PMP exam questions with ease at the exam.
The real PMP exam questions are not easier; but the more you practice, it would be better for you to face the actual PMP exam questions with ease at the exam.
Mock PMP Exam Questions
1. You are the project manager for a software project. You are in the process of establishing the policies, procedures and documentation for planning, developing, managing, executing and controlling the project schedule. You may use all of the following Tools & Techniques EXCEPT: (A) Expert judgment (B) Meetings (C) Decomposition (D) Analytical techniques |
2. The following are all examples of Organizational Process Assets EXCEPT: (A) Historical information (B) Organizational structure (C) Templates (D) Change control procedures |
3. You are the project manager of a $400 million construction project. You, along with your team, have identified and documented the specific actions to be performed to produce the project deliverables. What would be your immediate next action be?: (A) Develop Schedule (B) Collect Requirements (C) Sequence Activities (D) Select Sellers |
4. Your project involves the construction of a temporary concrete road. The road is expected to be in use for 6 months before it gets demolished. You have completed the laying of the temporary concrete road. But, the customer specification states that you have to wait for 28 days before using the road. Which of the following relationships most likely represents the relationship of the start of the use of the road to the completion of the construction of the road? (A) Finish-to-start with a 28 days lead (B) Finish-to-finish with a 6 months lag (C) Finish-to-start with a 28 days lag (D) Start-to-finish with a 28 days lag |
5. You are in the planning process of a $1b project. You realize that your schedule requires more resources in certain months of the project than that are available to you. Your senior management has clearly instructed that you will not be able to obtain any additional resources for the project. So, you instruct your planner to adjust the schedule to accommodate these constraints. What are you instructing the planner to do? (A) Crashing (B) Resource leveling (C) Programme Evaluation and Review Technique (D) Fast tracking |
You may also be interested in:
|
6. Projects are a means of achieving objectives within an organization's strategic plan. Which of the following statements is NOT true about projects? (A) Every project creates a unique product, service or result (B) The duration of the project is short (C) Repetitive elements may be present in some project deliverables and activities (D) A project can involve a single individual |
7. The project charter contains high level information. Which of the following elements is NOT typically found in a project charter? (A) Project purpose or justification (B) Summary milestone schedule (C) Work packages (D) Stakeholder list |
8. The key benefit of performing quantitative risk analysis is that it produces quantitative risk information to support decision making in order to reduce project uncertainty. Which of the following is NOT a commonly used quantitative risk anlaysis and modeling technique? (A) Tornado diagram (B) Decision tree diagram (C) Monte Carlo Technique (D) Delphi Technique |
9. An organization invests certain amount of money into a project and makes $48,400 after 2 years. If the rate of return is 10%, how much money did the organization invest in the project? (A) $44,000 (B) $40,000 (C) $47921 (D) $47446 |
10. An organization is trying to choose between two projects. Project A has an estimated cost of $400,000 and an estimated NPV of $90,000. Another project B has an estimated cost of $360,000 and an estimated NPV of $110,000. If the senior management decides to go ahead with project B, what would be the opportunity cost? (A) $40,000 (B) $20,000 (C) $90,000 (D) $110,000 |
Answers to the above questions are available at:
Conclusion
I am confident that you would find the above questions helpful in your PMP exam Prep. The answers and detailed explanations with references for the above PMP exam questions would be uploaded soon. I would also update this list with more questions. IF you have any comment/ suggestions/ feedback on the above PMP exam questions, you may leave your comment below.Tuesday, January 12, 2016
Answer Key for Oliver Lehmann PMP Exam
By
With
6 comments:
Oliver F. Lehmann is one of the well known project management trainers. Being a trainer since 1995, he primarily focusses on PMP certification preparation. His 75 free sample questions (PMP® Exam Self-Assessment Test) is very popular. If you have not tried the test yet, please STOP reading this article.
He has given the answers and relevant references for all the 75 questions. He has not given any answer explanations, probably to encourage candidates to research themselves. I do encourage you to think and do a research before reading further on.
Since the cost and duration are the same for both projects, let us ignore those data; we will look into the returns/ benefits of the project only to compare.
Net Present Value (NPV) = FV/(1+r)t, where
FV = Future Value
r = rate of interest
t = time period
So, the NPV of project 1 considering first three years
= 120000 / 1.05 + 120000 / 1.052 + 120000 / 1.053
= $326790
NPV of project 2 considering first three years
= 15000 / 1.05 + 125000 / 1.052 + 220000 / 1.053
= $317709
Comparing the two values, project #1 is better. By, what percentage?
= (326790-317709) / 317709
= 0.029
= 2.90% (approximately 3%)
So, the first project is more attractive by approximately 3%.
He has given the answers and relevant references for all the 75 questions. He has not given any answer explanations, probably to encourage candidates to research themselves. I do encourage you to think and do a research before reading further on.
Question No. 2 from Oliver Lehmann PMP Exam Self Assessment Test
I took question #2 from the sample test to solve here. Read further only if you have failed to solve yourself and really need a guidance.Source: http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm |
Answer Key for Oliver Lehmann PMP Exam Question No. 2
There are two projects in the question. We need to choose the project with a better returns based on the Net Present Value (NPV). The below table shows the given data.Project # | Duration | Cost | Returns |
---|---|---|---|
1 | 9 months | $250,000 | $120,000/ year |
2 | 9 months | $250,000 | 1st year: $15,000 2nd year: $125,000 3rd year: $220,000 |
Since the cost and duration are the same for both projects, let us ignore those data; we will look into the returns/ benefits of the project only to compare.
Net Present Value (NPV) = FV/(1+r)t, where
FV = Future Value
r = rate of interest
t = time period
So, the NPV of project 1 considering first three years
= 120000 / 1.05 + 120000 / 1.052 + 120000 / 1.053
= $326790
NPV of project 2 considering first three years
= 15000 / 1.05 + 125000 / 1.052 + 220000 / 1.053
= $317709
Comparing the two values, project #1 is better. By, what percentage?
= (326790-317709) / 317709
= 0.029
= 2.90% (approximately 3%)
So, the first project is more attractive by approximately 3%.
Conclusion
Hope the above explanation helps. If you need any further information/ help regarding this question, please leave a comment below.Monday, November 23, 2015
How did I prepare for PMI-RMP Certification?
By
With
No comments:
What is PMI-RMP® Certification? How did I prepare for PMI-RMP® Certification? You will find answers to these questions in this article.
PMI-RMP® Certification is the prestigious Risk Management Professional Certification from PMI (Project Management Institute). It demonstrates your ability to identify and analyze project risks, avoid/ transfer/ mitigate threats and capitalize on opportunities. PMI states that
I believe that only practice can help you. I believe that most of the candidates who prepare for the risk management exam are already certified PMPs. So, they have the knowledge and basic understanding of how the risks are identified, assessed, risk responses planned, monitored and controlled. So, all they need is to practice more and more mock tests/ practice questions to get it right. Please go ahead and successfully obtain your PMI-RMP Credential!
PMI-RMP® Certification is the prestigious Risk Management Professional Certification from PMI (Project Management Institute). It demonstrates your ability to identify and analyze project risks, avoid/ transfer/ mitigate threats and capitalize on opportunities. PMI states that
83% of organizations that are high performers in project management practice risk management frequently while just 49 percent of low performers do so (Pulse of the Profession®: Capturing the Value of Project Management, February 2015)
You may also be interested in:
How did I prepare for PMI-RMP Certification?
I became a Certified Risk Management Professional and earned my PMI-RMP® Credential about two years back. In this article, I would like to share the various mock exams I tried and the scores I obtained in those. I am just jotting down the journey towards obtaining PMI-RMP® Certification.Date of the Mock Test | Service Provider | Description | No. of questions | Score Obtained | |
---|---|---|---|---|---|
1 | 24-06-2013 | SimpliLearn | Free PMP test | 175 | 78.9 % |
2 | 15-07-2013 | Ucertify | Free RMP Test | 15 | 73 % |
3 | 16-07-2013 | Ucertify | Chapter Quiz | 26 | 77 % |
4 | 17-07-2013 | The PM Instructors | Free PMI-RMP Questions | 20 | 85 % |
5 | 22-07-2013 | Rita Mulcahy | Pretest | 25 | 84 % |
6 | 28-07-2013 | Abdulla J. Alkuwaiti | Practice Questions | 65 | 87.1 % |
7 | 29-07-2013 | PMXCEL.com | Sample Quiz | 25 | 92 % |
8 | 02-08-2013 | Head First PMP | Risk Management Chapter Questions | 20 | 95 % |
9 | 03-08-2013 | VTC | RMP Part 1 | 40 | 95 % |
10 | 04-08-2013 | VTC | RMP Part 2 | 50 | 88 % |
11 | 05-08-2013 | Scordo | Risk Management Questions | 10 | 80 % |
12 | 06-08-2013 | Oliver Lehmann | PMP Test | 75 | 80 % |
13 | 06-08-2013 | VTC | RMP Part 3 | 125 | 89 % |
14 | 07-08-2013 | VTC | PMI-SP Part 1 | 40 | 85 % |
15 | 10-08-2013 | Rita Mulcahy | Human Resource Chapter | 34 | 76 % |
16 | 10-08-2013 | Rita Mulcahy | Quality Chapter | 35 | 91 % |
17 | 12-08-2013 | Rita Mulcahy | Time Chapter | 38 | 94.7 % |
18 | 14-08-2013 | Edwel | Free PMP Exam | 200 | 79 % |
19 | 12-08-2013 | Rita Mulcahy | Cost Chapter | 38 | 94.7 % |
20 | 15-08-2013 | Rita Mulcahy | Procurement Chapter | 40 | 92.5 % |
I believe that only practice can help you. I believe that most of the candidates who prepare for the risk management exam are already certified PMPs. So, they have the knowledge and basic understanding of how the risks are identified, assessed, risk responses planned, monitored and controlled. So, all they need is to practice more and more mock tests/ practice questions to get it right. Please go ahead and successfully obtain your PMI-RMP Credential!